| 1920 - 956 페이지
...comply with the provisions of the contract. The city, if not at fault, may give the contractor ten days' written notice; and at the end of that time,...if the contractor continues to neglect the work the city may * « « terminate the employment of the contractor under this agreement, and take possession... | |
| American Railway Engineering Association - 1914 - 1224 페이지
...this contract. t- i Annulment. ' (b) The. Company, if not at fault, may give the Contractor ten (ip) days' written notice, and at the end of that time...terminate the employment of the Contractor under this agreeent and take possession of «bc;ipfeniises and of all materials, tools and appliances thereon,... | |
| Clinton Hamlin Blake - 1916 - 360 페이지
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| Fred Lavis - 1917 - 648 페이지
...provisions of this contract. Annulment. (b) The Company, if not at fault, may give the Contractor ten (10) days' written notice. and at the end of that time,...possession of the premises and of all materials, tools and applianees thereon, and employ such forces as may be necessary to finish the work. In such case the... | |
| Calvin Frank Allen - 1917 - 468 페이지
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| Calvin Frank Allen - 1917 - 472 페이지
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| 1917 - 550 페이지
...after giving the Contractor seven days. written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the-Contractor shall not be... | |
| 1919 - 476 페이지
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| Calvin Frank Allen - 1919 - 486 페이지
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| American Institute of Architects - 1920 - 212 페이지
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| |