ÆäÀÌÁö À̹ÌÁö
PDF
ePub

The above expenditures had resulted in protecting a part of the harbor, giving a secure harbor of refuge for many vessels that trade near this port.

During the fiscal year ending June 30, 1893, the expenditures were $29,750.97. At the close of the fiscal year 1892 work on the breakwater was in progress under a contract with William S. White, of Rockland, Me. This contract was completed in November, 1892. At that date the breakwater had been practically completed to a point about 2,215 feet from the shore. In December, 1892, a contract was made involving the expenditure of the appropriation of July 13, 1892, for continuing the construction of the breakwater. The work was in progress at the close of the fiscal year 1893, about 23,460 tons of stone having been deposited. The price is 73 cents per ton of 2,000 pounds of stone, deposited in place.

An examination of Rockland Harbor, under the provisions of act of Congress of July 13, 1892, was made and report thereon submitted August 17, 1892. (See below, page 37.)

[blocks in formation]

July 1, 1893, outstanding liabilities..

20, 863.55

$1.330.91

July 1, 1893, amount covered by uncompleted contracts.

15, 240.94

16,571.85

4, 291.70

July 1, 1893, balance available.....

412,500.00

Amount (estimated) required for completion of existing project.. Amount that can be profitably expended in fiscal year ending June 30, 1895 100, 003. 00 Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867 and of sundry civil act of March 3, 1893. (See Appendix A 10.)

11. Kennebec River, Maine.-Before the improvements were com. menced the main channel of the river between the foot of Swan Island and Gardiner was obstructed by shoals near Beef Rock, with only 10 feet of water at mean low tide, by dangerous sunken ledges in Lovejoy Narrows, by a shoal below South Gardiner with only 8 feet on it at mean low tide, and by a ledge at Nehumkeg Island. The steamboat channel to the west of Swan Island (Hatchs Rock) was obstructed by a shoal over which there was only 73 feet of water, and the channel between Gardiner and Augusta, a distance of 6 miles, was obstructed by shoals which gave only a navigable depth of 33 feet of water in low summer tides.

Appropriations were made at various times between 1827 and 1852 for improving the river, but the first regular project was adopted only in 1866, and was for removing rocks and straightening and deepening the upper part of the river. The estimated cost was $50,000.

In 1868 the project was amended so as to give a wider channel, and the estimate was increased to $80,000. In 1871 the project was extended, the additional cost being estimated at $13,000, making the estimate for the entire project $93,000. It was again extended in 1872, to include the removal of ledges in Lovejoy Narrows, at an additional estimated cost of $30,603.61. This project was modified in 1873, and as modified was completed in 1877.

In 1881 a project was adopted for the improvement of the channel west of Swan Island, and near the north end of it. The estimated cost of this project, which was completed in 1883, was $20,500.

The river and harbor act of 1886 provided for a new survey of the river from Bath to Augusta. This survey was made in 1887, and a project submitted for the further improvement of the river, giving 12 feet clear depth at low tide up to the Upper Sands Bar, near South Gardiner, 10 feet from thence to Hinckley Shoal, and 8 feet from thence to Augusta, together with an improvement of the steamboat channel west of Swan Island to 9 feet at mean low tide. The estimated cost of this project was $410,500, which estimate was subsequently increased to $428,500.

In August, 1892, the project was revised, and a general project for the improvement adopted, as follows: For a channel depth of 13 feet, up as far as Sands Island; 12 feet from thence to Hinckley Shoal, and 10 feet from thence to Augusta; a steamboat channel, 9 feet deep, west of Swan Island, and the removal of old bridge piers at Hallowell, all the above depths being referred to mean low tide. The estimated cost of the revised project is $388,500.

The total expenditures for the river up to June 30, 1892, were $288,792.82.

By the expenditure of this sum the channel near Beef Rock has been improved to give a clear depth of over 12 feet, the dangerous rocks in Lovejoy Narrows have been removed to a depth of 12 feet, and the channel through the Narrows straightened, the shoal near South Gardiner was deepened from 8 feet to 10 feet, the ledge at Nehumkeg was removed to 12 feet, the steamboat channel west of Swan Island has been deepened to 9 feet, and near the head of it to 10 feet, the channel between Gardiner and Augusta has been deepened to 7 feet between Gardiner and Hallowell, and to 63 feet between Hallowell and Augusta, and the old piers of the bridge at Hallowell have been removed.

Some shoaling has since taken place between Gardiner and Augusta, and some on the bar below South Gardiner, but on the whole a decided betterment of navigation has been accomplished.

The expenditures for the year ending June 30, 1893, have been $21,415.57. A jetty, about 1,500 feet long, was built at Upper Sands Bar, and some work was also done on Beef Rock Jetty, in both cases by purchase of material in open market.

Contracts were made for dredging at and near Gardiner, and for removal of ledge in Lovejoy Narrows. In both cases work was commenced during the early part of June, and was in progress at the close of the year, but not sufficiently advanced to afford material advantage to navigation.

[blocks in formation]

July 1, 1893, outstanding liabilities.

$2,509.50

July 1, 1893, amount covered by uncompleted contracts

[blocks in formation]

July 1, 1893, balance available

Amount (estimated) required for completion of existing project... Amount that can be profitably expended in fiscal year ending June 30, 1895 Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867 and of sundry civil act of March 3, 1893. (See Appendix A 11.)

[blocks in formation]

12. Harraseeket River, Maine.-The act approved March 3, 1881, provided that a survey be made of this river. The survey was made in July of that year, and a report submitted in December by the engineer of the district.

The river empties into Casco Bay at Stocksbridges Point, about 12 miles northeast of Portland. From Stocksbridges Point up to Westons Point the depth of water is no less than 10 feet at mean low tide, with no obstruction to navigation.

From Westons Point up to Freeport Landing, a distance of 4,500 feet, the depth diminishes so that for the greater part of the distance the bottom of the river is 34 feet out of water at mean low tide. The rise and fall of tides here is 9 feet. The project recommended in 1881 was the dredging of a channel not less than 60 feet wide and 3 feet deep at mean low tide up to Freeport, and a turning basin 180 feet wide at the head of the channel. The estimated cost of the improvement recommended was $13,000.

No appropriation was made for the work, however, and a new survey was ordered in the river and harbor act of 1888. A project for the improvement was submitted January 4, 1889. This project was on a somewhat larger scale than the one previously suggested, and contemplated a depth of channel of 5 feet at mean low tide, which would give about 14 feet at high tide. The estimated cost of the project was $36,000.

There had been no expenditures up to the close of the fiscal year ending June 30, 1892, and no work had been done, as it was not deemed expedient to expend any money on the improvement until sufficient funds had been appropriated to accomplish more work than could be done with the amount at that time available.

The expenditures during the year ending June 30, 1893, were $47.80. No work was done.

Proposals for dredging were twice invited by public advertisements, but the prices were regarded as high, and all the bids were rejected. The work will be readvertised at an early date.

[blocks in formation]

13. Portland Harbor, Maine.-The entrance to the main part of the harbor of Portland or the anchorage has always been good, but prior to the improvements made by the Government the approach to the inner harbor was obstructed by a shoal known as the middle ground, over which the depth was only from 8 to 10 feet at mean low tide, while between it and Stamford Ledge the greatest available depth was only 16 feet. Besides, the best part of the wharf front of the city was exposed to the swell from the Atlantic, which sometimes made it dangerous for vessels to lie at the docks, and the depth along this front was in some places as little as 4 feet, making a part of it unavailable for commercial purposes.

The first work of improvement undertaken by the Government was the construction of the breakwater. This was begun as early as 1836, It was completed in 1874.

The project for the improvement of the harbor by deepening its waters was first undertaken by authority of act of Congress of 1868. The project was at that time to excavate a channel 300 feet wide through the southern slope of the middle ground to a depth of 20 feet .at mean low tide.

In 1870 the project was amended so as to provide for a channel 400 feet wide, and in 1871 it was again amended so as to provide for a width of 500 feet.

In 1872 the improvement of Back Cove was added to the project, and in December of that year the project was further amended by providing for the dredging of the inner harbor up to the harbor commissioner's lines to a depth of 16 feet. By 1876 all the contemplated improvements had been executed except some dredging in the inner harbor.

In 1881 Congress made an appropriation for the further improvement of the harbor, and a project was adopted looking to the entire removal of the shoal known as the middle ground, at an estimated cost of $160,000. The project was completed in 1885.

In 1886 the board of trade of Portland asked for the further improvement of the harbor to a depth of 29 feet at low tide, and in 1887 this project was adopted, the estimated cost being $135,000. This is the project now in process of execution.

The total amount expended on the harbor up to June 30, 1892, inclusive of all works of improvement, was $509,662.84. These expenditures resulted in giving, by means of the breakwater, partial protection to vessels at the lower wharves, and, by means of dredging, an available depth to navigation of 29 feet at mean low tide a depth sufficient to accommodate the largest class of ocean steamers.

The expenditures during the year ending June 30, 1893, have been $41,673.59. The work accomplished has been the widening of the 29foot entrance to the harbor, and the dredging of a shoal in the upper harbor to 16 feet at mean low tide. The project is now completed, giving a channel 500 feet wide and 29 feet deep at mean low tide, from the deep water of the anchorage to the lower wharves, with a large area, of the same depth, in front of the wharves.

[blocks in formation]

14. Channel in Back Cove, Portland, Maine.-Before any work was done toward improving Back Cove there existed no channel properly considered as such. Only the rudiments of an old channel existed, and, for the most part, even this was nearly dry at low tide.

The first project adopted had for its object the dredging of a channel 100 feet wide and 8 feet deep at mean low tide from Tukeys Bridge to the "stone shed wharves." The estimated cost was $10,000. The project was completed in 1874.

A survey was made in 1886, and a new project adopted having in view the widening of the channel to 300 feet and deepening it to 12 feet at mean low tide, with a turning basin at the upper end. The estimated cost was $180,000. This project is now in process of execution,

The expenditures, under the existing project, to the close of the fiscal year ending June 30, 1892, amounted to $51,691.61. At that date the channel had been extended for a distance of 4,050 feet, 12 feet deep at low tide, and 90 feet wide, and a turning basin 400 feet wide excavated. The expenditures during the fiscal year ending June 30, 1893, were $24,638.60. This amount was applied to widening the channel, under contract. The 12-foot channel is now 160 feet wide for a length of about 1,400 feet, 265 feet wide for a distance of about 1,400 feet more, and 90 feet wide the remaining length.

Proposals for dredging, involving the expenditure of the appropriation of July 13, 1892, were twice invited, but each time the prices were high, and the bids were all rejected.

July 1, 1892, balance unexpended................

Amount appropriated by act approved July 13, 1892.

June 30, 1893, amount expended during fiscal year..

July 1, 1893, balance unexpended................

Amount (estimated) required for completion of existing project...... Amount that can be profitably expended in fiscal year ending June 30, 1895 Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867 and of sundry civil act of March 3, 1893. (See Appendix A 14.)

$24, 558.39 20,000.00

44, 558, 39 24,638.60

19, 919. 79

83.750.00

50,000.00

15. Saco River, Maine.-The first work done on the Saco River was in 1827, when an appropriation was made for the erection of piers, placing beacons or buoys, and removing obstructions. Prior to this the depth of water on the bar was only about 2 feet at mean low tide, while much of the river was deeper. The entrance was also dangerous in rough weather, and the numerous projecting rocks and ledges in the river proper, in connection with the swift currents, made its navigation dangerous.

In 1866 a plan was proposed for the improvement of the mouth of the river, and a project adopted in 1867. The project was for the construction of a breakwater at the mouth of the river, the removal of sunken rocks, and the rebuilding of some of the most important piers, against which vessels might drift without damage. The project was completed in 1873 at a cost of $169,275.

Nothing more was done on the Saco until 1883, when a resurvey of the breakwater was made and a new project submitted for raising and repairing it and extending it out to Sharps Ledge.

The river and harbor act of 1884 directed a survey to be made of the river. This was done in 1885, and a project submitted for the improvement of the river proper from its mouth to the head of navigation. In 1886 and 1888 appropriations were made for repairing and raising the breakwater and for improving the river. In 1890 the two projects were combined, so that the one now in process of execution is for improving the Saco River, including the breakwater and the construction of a proposed jetty opposite the same.

The total expenditures on both river and breakwater up to June 30, 1892, were $256,937.22, and resulted in removing the dangerous ledges, in constructing piers to prevent vessels from being swept on the rocks, in constructing a substantial breakwater on the north side of the entrance, and the partial construction of a jetty on the south side of the entrance to contract the channelway with a view to obtaining a greater depth over the bar.

« ÀÌÀü°è¼Ó »