페이지 이미지
PDF
ePub

moored on the south side of the works, by which the stones were lifted from the stone barges and placed on the car; the car was then pushed under one of the travellers, the stone raised by a hand-crab which was placed at the east end of the works till it cleared the car, and drawn forward till opposite the desired point by a steam crab, which was likewise at the east end of the works, and driven by the same engine which worked the dredges, both sets of machinery rarely being worked together. This apparatus was not mounted till the beton in the two lower sections of the caisson had all been put in.

Soon after the caisson was brought into position the rectangular openings into the lower chambers had been surmounted by timber boxes; this was continued from time to time as the sinking progressed, the successive sections of these well walls being made of such height as was found most convenient. When the hollow walls of the caisson had been filled with beton a second section was built above it; this section was an open frame structure, covered with threeinch oak plank dressed in a planer, and similar to the caissons used at Piers 1 and 3; the long sides were given a batter of one in sixteen, but the short sides of the starlings were built plumb; additional lengths were also put on the gas pipes. This section, like the lower one, was filled with beton, about one-half the full amount being put in before starting the machinery. The beton was mixed upon the platform, thrown at once into the caisson, and beaten down with a paving maul. It set rapidly, forming a satisfactory compound; the caisson thus became merely the wooden covering of a single artificial stone or monolith, of the form most convenient for the work, and which carried the masonry of the pier above.

On the 11th of December the ice closed at the bridge line, and the river froze across. A week later the ice, which was still thin, began to rot rapidly under a strong sun, and on the 19th it broke up and went out. No serious damage was done, but a large sheet of ice, jamming above the draw rest, forced inwards the ice along the north shore, which, swinging on a pivot, about the anchor piles above the works, tore out two piles on the north-west corner of the false-works of this pier, the injury being done at one of those points where the exposure was supposed to be least. The damage was soon repaired; one of the piles had only been bent over, and was drawn back into place; the other,

the corner pile, was destroyed, but the platform was made secure by bracing below.

On the 28th of December the machinery was started; a few unimportant changes were found desirable, but its performance was, on the whole, very satisfactory. For the first week it was driven only by day, while the forces were being organized and drilled to their work. On Monday, the 4th of January, two gangs were put on, and the work proceeded both night and day. Each gang had a superintendent at its head, Mr. Tomlinson taking the day, and Mr. Bostwick the night shift; a master of machinery had general charge of the four dredges, while two mechanics were assigned to the care of each dredge; an engineman and fireman tended the engine on the lower floor, another man was given special charge of the donkey pump, and a spare machinist was employed upon odd jobs; a large gang of laborers completed this force; all the laborers worked under one foreman, and the majority of them were employed in wheeling off the sand, but twelve men were detailed to work the crabs on the top floor, and a few more to tend the suspension screws, while it occasionally became necessary to call in the entire force for the latter work. The same force was, of course, duplicated for the second shift; each gang worked from seven to seven o'clock, the day gang being allowed an hour at noon for dinner, and the night gang being furnished with hot coffee at midnight.

Eight vertical rods, graduated into feet and tenths, were fastened on the sides of the caisson, one at each end and shoulder, and one in the middle of each long side; they served as gauges to measure the descent, eight blocks placed on the platform opposite them, at an elevation of 109, answering as reading fingers; the gauge at the west nose was numbered one, that at the south-west shoulder, two, and so on continuously around the pier. The dredges were also numbered from one to four-the new dredge at the west end being number one. A full journal of the progress of the sinking was kept by the superintendent, from which a set of tables, illustrating the behavior of the pier and conditions. of the sinking, were prepared. These tables, which give the best illustration of the actual working of the plan, are printed in Appendix E.; they contain a statement of: 1st. The number of hours' work performed by each dredge, with

the estimated daily excavation. 2d. The readings of the gauges, daily progress, and average elevation of the cutting edge. 3d. The soundings opposite each gauge, and average elevation of the sand surrounding the pier. 4th. The displacement and the actual and effective weights of the pier. 5th. The area of the surface in contact with the sand, and the effective weight for each square foot of such surface in contact, with estimated friction.

The material dredged was at first a soft sticky silt, which could be handled only in connection with a large amount of water in the form of a thin, flowing mud. The work was conducted very carefully, the gauges were constantly watched, and the screws were tended continually; with these precautions little difficulty was experienced in keeping the pier true; after it had been sunk ten or twelve feet the surrounding sand answered as a guide, and less care was required to regulate the descent. Owing to the weight of the pier and the care with which the machinery had been arranged, the sinking proceeded at a very much more rapid rate than had yet been accomplished with the bottomless caissons, and exceeded the expectations of the engineers. On the 6th of January, only two days after both shifts of men had been put on, the work had to be suspended, because the beton could not be put in fast enough to keep pace with the descent, and from this time forward the chief difficulty lay in building up the pier rather than in sinking it. The water jets were found to be of less service than had been anticipated, the wedge-shaped edges feeding the sand to the dredges without their assistance; streams of water were occasionally passed through the pipes at the nose and shoulders, and all the outside pipes were lengthened as the height of the caisson was increased, but those in the crosswalls were allowed to be buried up in the beton.

On the 7th the machinery had to be stopped again, and it remained idle nearly a week; on the 8th the beton was nearly all in, reaching to the top of the second section. A third section had meanwhile been added, twelve feet high, the end walls of which were at first made only one-half this height, to facilitate handling the stone. On the 9th the river rose about a foot, causing a strong current on the south side of the works, which was found to have increased the depth of water from nine to seventeen feet, so that the pier began to settle over slightly, till held by the suspension screws; one hundred and fifty gunny

[graphic][merged small][merged small][merged small]
« 이전계속 »