도서 Contractor, then the time herein fixed for the completion of the work shall be extended...에 대해 검색한
" Contractor, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid ; but no such allowance shall be made unless a claim therefor is presented... "
The New York Supplement - 244 페이지
1904
전체보기 - 도서 정보

Reports of Cases at Law and in Chancery Argued and Determined in the ..., 228권

Illinois. Supreme Court - 1908
...earthquake or cyclone, or by abandonment of the work by employees through no fault of the contractor, then the time herein fixed for the completion of the...shall be extended for a period equivalent to the time Iqst by reason of any or all of the causes aforesaid." Article 8 stipulates that the owner shall pay...
전체보기 - 도서 정보

Reports of Cases at Law and in Chancery Argued and Determined in the ..., 255권

Illinois. Supreme Court - 1913
...the owner, or any of the other causes mentioned, the time fixed for the completion of the work should be extended for a period equivalent to the time lost by reason of any or all of said causes, which extended period should be determined and fixed by the architect. By the terms...
전체보기 - 도서 정보

Cases Decided in the United States Court of Claims ... with Report of ..., 131권

United States. Court of Claims, Audrey Bernhardt - 1955
...the Contractor, or any other Subcontractor, through no default of the Subcontractor, then the time fixed for the completion of the work shall be extended for a period equivalent to the time lost by any or all of the causes aforesaid, but no such 501 Findings of Fact allowance shall be made unless...
전체보기 - 도서 정보

The Federal Reporter: Cases Argued and Determined in the Circuit ..., 241-242권

1917
...or cyclone, or by the abandonment of the work by the employes through no fault of the subcontractor, then the time herein fixed for the completion of the...equivalent to the time lost by reason of any or all of the causes aforesaid," etc. This provision makes it clear that delays occasioned the plaintiff by...
전체보기 - 도서 정보

The Federal Reporter: Cases Argued and Determined in the Circuit ..., 149-150권

1907
...lightning, earthquake or cyclone, or by strikes or lockouts, through no default of the contractor, then the time herein fixed for the completion of the...equivalent to the time lost by reason of any or all of the causes aforesaid, but no such allowance shall be claimed or made unless a claim therefor shall...
전체보기 - 도서 정보

Atlantic Reporter, 59권

1905
...work by the act, neglect, delay, or default of the owner or the architects, » • • then the time fixed for the completion of the work shall be extended...equivalent to the time lost by reason of any or all of the causes aforesaid, but no such allowance shall be made unless a claim therefor is presented in...
전체보기 - 도서 정보

Atlantic Reporter, 88권

1914
...architects or of any other contractor employed by the owner on the work, the time fixed for completion "shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid." But It was' also provided that "no such allowance will be made unless a claim...
전체보기 - 도서 정보

The Southwestern Reporter, 66권

1902
...abandonment of the work by the employC-s of the contractor through no fault of theirs, then the time fixed for the completion of the work shall be extended for a period equivalent to the time thus lost," etc. It thus appears that the contractors stipulated what they might claim for themselves...
전체보기 - 도서 정보

The Southwestern Reporter, 147권

1912
...prosecution or completion of the work by the act, neglect, or default of the owner or architect that the time herein fixed for the completion of the work shall be extended for a period equal to the time lost by reason of any such cause. But It also provides that no such allowance shall...
전체보기 - 도서 정보

The Southwestern Reporter, 91권

1906
...the owner or the architects, or of any other contractor employed by the owner upon the work, * * * then the time herein fixed for the completion of the work shall be extended," etc. The undisputed evidence shows that the contract ] with the brick company was made by the contractors...