페이지 이미지
PDF
ePub

last line will not cross the south fork, and that the land will not be "on both sides of the two main forks of Duck river."

error.

But this objection will not be removed or diminished by the instruction required by the plaintiff in Nor can the land be so surveyed as that the last line shall cross the south fork. From the termination of the third line, it is necessary to proceed to the beginning, and the platt shows us that the south fork does not run between the two points. It cannot be brought between them, if at all, without extending the third line an immense distance, and changing the whole figure of the platt, or entirely disregarding the act of Assembly, which directs lands to be taken up by lines running with the cardinal points, except in particular cases, of which this is not one.

Judgment affirmed with costs.

1822.

Tayloe

V.

Sandiford.

[COMMON LAW.]

TAYLOE V. T. & S. SANdiford.

In general, a sum of money in gross, to be paid for the non-performance of an agreement, is considered as a penalty, and not as liquidated damages.

A fortiori, when it is expressly reserved as a penalty.

Thus, where in a building contract, the following covenant was con

tained: "The said houses to be completely finished on or before the

1822.

Tayloe

V.

Sandiford.

24th of December next, under a penalty of 1000 dollars, in case of failure;" it was held, that this was not intended as liquidated damages for the breach of that single covenant only, but applied to all the covenants made by the same party in that agreement; that it was in the nature of a penalty, and could not be set off in an action brought by the party to recover the price of the work.

An agreement to perform certain work within a limited time, under a certain penalty, is not to be construed as liquidating the damages which the party is to pay for the breach of his covenant.

The case of Fletcher v. Dycke, 2 Term Rep. 32. commented on, and distinguished from the present.

A person owing money under distinct contracts, has a right to apply his payments to whichever debt he may choose, and this power may be exercised without any express direction given at the time.

A direction may be evidenced by circumstances, as well as by words: and a positive refusal to pay one debt, and an acknowledgment of another, with a delivery of the sum due upon it, would be such a circumstance.

Feb. 5th.

Feb. 12th.

THIS cause was argued by Mr. Jones, and Mr. Hay, for the plaintiff in error, and by Mr. Key' for the defendants in error.

Mr. Chief Justice MARSHALL delivered the opinion of the Court.

This is a writ of error to a judgment of the Circuit Court of the county of Alexandria, rendered in an action of assumpsit, brought by T. & S. Sandiford against John Tayloe. It appeared on the trial of the cause, that on the 13th of May, 1816, the parties entered into a written contract, by

{ a They cited 2 Comyn on Contracts, 528-539, and the cases there collected. Fletcher v. Dycke, 2 T. R. 32.

b He cited 4 Cranch, 317. 6 Cranch, 9. Dennis v. Cummins, 3 Johns. Cas. 297. Smith v. Dickenson, 3 Bos. & Pul. 630. Bank of Columbia v. Patterson, 7 Cranch, 299.

which the defendants in error undertook to build for the plaintiff three houses on the Pennsylvania avenue in the city of Washington. On the 18th day of the same month, the parties entered into a contract, under seal, for the building of three additional houses, at a stipulated price. This contract contains the following covenant: "The said houses to be completely finished on or before the 24th day of December next, under a penalty of one thousand dollars, in case of failure."

The parties entered into a third verbal contract for some additional work, to be measured, and paid for according to measurement.

These three houses were not completed by the day, and the plaintiff in error claimed the sum of 1,000 dollars, as stipulated damages, and retained it out of the money due to the defendants in error. This suit was, thereupon, brought; and, on the trial of the cause, the defendant in the Circuit Court claimed to set off in this action 1,000 dollars, as in the nature of stipulated damages; but the Court overruled this claim, and decided that the said sum of 1,000 dollars had been received in the nature of a penalty, and could not be set off in this action.

The defendant then moved the Court to instruct the jury, that "upon the evidence offered, if believed, the plaintiffs were not entitled to recover in this action the said sum of 1,000 dollars, inasmuch as the same, if due at all, was due under a contract under seal, and that the declarations of the defendant, and the understanding between the parties as to the reservation of the said 1,000 dollars, given in evi

1822.

Tayloe

V.

Sandiford.

1822.

Tayloe

V..

Sandiford.

dence as aforesaid, was competent and sufficient evidence of the defendants' intention to apply his payment to the extinguishment, in the first instance, of such parts of the said moneys as were due by simple contract, and to reserve the 1,000 dollars out of the money due under the said original contract." This instruction the Court refused to give; and did instruct the jury "that it was competent to the plaintiffs to recover the said 1,000 dollars in this action, unless they should be satisfied by the evidence that the defendant, at the time of paying the money, had expressly directed the same, or a sufficient part thereof, to the payment of the 1,500 dollars due on the simple contract."

To both these opinions the defendant excepted; and the jury having given a verdict for the plaintiff in the Circuit Court, this writ of error was brought to the judgment rendered thereon.

It is contended, by the plaintiff in error, that the Circuit Court erred.

1st. In overruling the claim to off-set the 1,000 dollars mentioned in the agreement.

2d. In declaring that the plaintiff in that Court might so apply the payments made, as to discharge the contract under seal, and leave the sum retained by the defendant in that Court, to be demanded under the simple contract.

1. Is the sum of 1,000 dollars mentioned in the agreement of the 13th of May, to be considered as a penalty, or as stipulated damages?

The words of the reservation are, "The said house to be completely finished on or before the 24th day

of December next, under the penalty of 1,000 dollars, in case of failure."

In general, a sum of money in gross, to be paid for the non-performance of an agreement, is considered as a penalty, the legal operation of which is, to cover the damages which the party, in whose favour the stipulation is made, may have sustained from the breach of contract by the opposite party. It will not of course be considered as liquidated damages; and it will be incumbent on the party who claims them as such, to show that they were so considered by the contracting parties. Much stronger is the inference in favour of it's being a penalty, when it is expressly reserved as one. The parties themselves denominate it a penalty; and it would require very strong evidence to authorize the Court to say that their own words do not express their own intention. These writings appear to have been drawn on great deliberation; and no slight conjecture would justify the Court in saying that the parties were mistaken in the import of the terms they have employed.

The counsel for the plaintiff in error supposes, that the contract furnishes clear evidence that the parties intended this sum as liquidated damages. The circumstance, that it is annexed to the single covenant, stipulating the time when the work shall be completed, is considered as showing that it was intended to fix the damages, for the breach of that covenant.

Without deciding on the weight to which this argument would be entitled, if supported by the fact, the court cannot admit that it is so supported. The engagement, that the said houses shall be complete

[blocks in formation]

1822.

Tayloe

V.

Sandiford.

« 이전계속 »