Federal grants from all sources in excess of 80 per centum of the cost of such project.

(b) Any publicly owned treatment works constructed with or eligible for Federal financial assistance under this Act in a State between June 30, 1956, and June 30, 1966, which was approved by the State water pollution control agency and which the Administrator finds meets the requirements of section 8 of this Act prior to the date of enactment of the Federal Water Pollution Control Act Amendments of 1972 but which was constructed without assistance under such section 8 or which received such assistance in an amount less than 30 per centum of the cost of such project shall qualify for payments and reimbursement of State or local funds used for such project from sums allocated to such State under this section in an amount which shall not exceed the difference between the amount of such assistance, if any, received for such project and 30 per centum of the cost of such project.

(c) No publicly owned treatment works shall receive any payment or reimbursement under subsection (a) or (b) of this section unless an application for such assistance is filed with the Administrator within the one year period which begins on the date of enactment of the Federal Water Pollution Control Act Amendments of 1972. Any application filed within such one year period may be revised from time to time, as may be necessary.

(d) The Administrator shall allocate to each qualified project under subsection (a) of this section each fiscal year for which funds are appropriated under subsection (e) of this section an amount which bears the same ratio to the unpaid balance of the reimbursement due such project as the total of such funds for such year bears to the total unpaid balance of reimbursement due all such approved projects on the date of enactment of such appropriation. The Administrator shall allocate to each qualified project under subsection (b) of this section each fiscal year for which funds are appropriated under subsection (e) of this section an amount which bears the same ratio to the unpaid balance of the reimbursement due such project as the total of such funds for such year bears to the total unpaid balance of reimbursement due all such approved projects on the date of enactment of such appropriation.

(e) There is authorized to be appropriated to carry out subsection (a) of this section not to exceed $2,600,000,000 and, to carry out subsection (b) of this section, not to exceed $750,000,000. The authorizations contained in this subsection shall be the sole source of funds for reimbursements authorized by this section.

(f) (1) In any case where all funds allotted to a State under this title have been obligated under section 203 of this Act, and there is construction of any treatment work project without the aid of Federal funds and in accordance with all procedures and all requirements applicable to treatment works projects, except those procedures and requirements which limit construction of projects to those constructed with the aid of previously allotted Federal funds, the Administrator, upon his approval of an application made under this subsection therefor, is authorized to pay the Federal share of the cost of construction of such project when additional funds are allotted to the State under this title if prior to the construction of the project the Administrator

approves plans, specifications, and estimates therefor in the same manner as other treatment works projects. The Administrator may not approve an application under this subsection unless an authorization is in effect for the future fiscal year for which the application requests payment, which authorization will insure such payment without exceeding the State's expected allotment from such authorization. (2) In determining the allotment for any fiscal year under this title, any treatment works project constructed in accordance with this section and without the aid of Federal funds shall not be considered completed until an application under the provisions of this subsection with respect to such project has been approved by the Administrator, or the availability of funds from which this project is eligible for reimbursement has expired, whichever first occurs.

AUTHORIZATION

SEC. 207. There is authorized to be appropriated to carry out this title, other than sections 206 (e), 208 and 209, for the fiscal year ending June 30, 1973, not to exceed $5,000,000,000, for the fiscal year ending June 30, 1974, not to exceed $6,000,000,000, and for the fiscal year ending June 30, 1975, not to exceed $7,000,000,000, and, subject to such amounts as are provided in appropriation Acts for the fiscal year ending September 30, 1977, $1,000,000,000 for the fiscal year ending September 30, 1978, $4,500,000,000 and for the fiscal years ending September 30, 1979, September 30, 1980, September 30, 1981, and September 30, 1982, not to exceed $5,000,000,000 per fiscal year.

AREAWIDE WASTE TREATMENT MANAGEMENT

SEC. 208. (a) For the purpose of encouraging and facilitating the development and implementation of areawide waste treatment management plans

(1) The Administrator, within ninety days after the date of enactment of this Act and after consultation with appropriate Federal, State, and local authorities, shall by regulation publish guidelines for the identification of those areas which, as a result of urban-industrial concentrations or other factors, have substantial water quality control problems.

(2) The Governor of each State, within sixty days after publication of the guidelines issued pursuant to paragraph (1) of this subsection, shall identify each area within the State which, as a result of urban-industrial concentrations or other factors, has substantial water quality control problems. Not later than one hundred and twenty days following such identification and after consultation with appropriate elected and other officials of local governments having jurisdiction in such areas, the Governor shall designate (A) the boundaries of each such area, and (B) a single representative organization, including elected officials from local governments or their designees, capable of developing effective areawide waste treatment management plans for such area. The Governor may in the same manner at any later time identify any additional area (or modify an existing area) for which he determines areawide waste treatment management to be appropriate, designate the boundaries of such area, and designate an organiza

tion capable of developing effective area wide waste treatment management plans for such area.

(3) With respect to any area which, pursuant to the guidelines published under paragraph (1) of this subsection, is located in two or more States, the Governors of the respective States shall consult and cooperate in carrying out the provisions of paragraph (2), with a view toward designating the boundaries of the interstate area having common water quality control problems and for which areawide waste treatment management plans would be most effective, and toward designating, within one hundred and eighty days after publication of guidelines issued pursuant to paragraph (1) of this subsection, of a single representative organization capable of developing effective area wide waste treatment management plans for such area.

(4) If a Governor does not act, either by designating or determining not to make a designation under paragraph (2) of this subsection, within the time required by such paragraph, or if, in the case of an interstate area, the Governors of the States involved do not designate a planning organization within the time required by paragraph (3) of this subsection, the chief elected officials of local governments within an area may by agreement designate (A) the boundaries for such an area, and (B) a single representative organization including elected officials from such local governments, or their designees, capable of developing an area wide waste treatment management plan for such area.

(5) Exiting regional agencies may be designated under paragraphs (2), (3), and (4) of this subsection.

(6) The State shall act as a planning agency for all portions of such State which are not designated under paragraphs (2), (3), or (4) of this subsection.

(7) Designations under this subsection shall be subject to the approval of the Administrator.

(b)(1) (A) Not later than one year after the date of designation of any organization under subsection (a) of this section such organization shall have in operation a continuing area wide waste treatment management planning process consistent with section 201 of this Act. Plans prepared in accordance with this process shall contain alternatives for waste treatment management, and be applicable to all wastes generated within the area involved. The initial plan prepared in accordance with such process shall be certified by the Governor and submitted to the Administrator not later than two years after the planning process is in operation.

(B) For any agency designated after 1975 under subsection (a) of this section and for all portions of a State for which the State is required to act as the planning agency in accordance with subsection (a) (6), the initial plan prepared in accordance with such process shall be certified by the Governor and submitted to the Administrator not later than three years after the receipt of the initial grant award authorized under subsection (f) of this section.

(2) Any plan prepared under such process shall include, but not be limited to

(A) the identification of treatment works necessary to meet. the anticipated municipal and industrial waste treatment needs of

the area over a twenty-year period, annually updated (including an analysis of alternative waste treatment systems), including any requirements for the acquisition of land for treatment purposes; the necessary waste water collection and urban storm water runoff systems; and a program to provide the necessary financial arrangements for the development of such treatment works, and an identification of open space and recreation opportunities that can be expected to result from improved water quality, including consideration of potential use of lands associated with treatment works and increased access to water-based recreation;

(B) the establishment of construction priorities for such treatment works and time schedules for the initiation and completion of all treatment works;

(C) the establishment of a regulatory program to

(i) implement the waste treatment management requirements of section 201 (c),

(ii) regulate the location, modification, and construction of any facilities within such area which may result in any discharge in such area, and

(iii) assure that any industrial or commercial waste discharged into any treatment works in such area meet applicable pretreatment requirements;

(D) the identification of those agencies necessary to construct, operate, and maintain all facilities required by the plan and otherwise to carry out the plan;

(E) the identification of the measures necessary to carry out the plan (including financing), the period of time necessary to carry out the plan, the costs of carrying out the plan within such time, and the economic, social, and environmental impact of carrying out the plan within such time;

(F) a process to (i) identify, if appropriate, agriculturally and silviculturally related nonpoint sources of pollution, including return flows from irrigated agriculture, and their cumulative effects, runoff from manure disposal areas, and from land used for livestock and crop production, and (ii) set forth procedures and methods (including land use requirements) to control to the extent feasible such sources;

(G) a process of (i) identify, if appropriate, mine-related sources of pollution including new, current, and abandoned surface and underground mine runoff, and (ii) set forth procedures and methods (including land use requirements) to control to the extent feasible such sources;

(H) a process to (i) identify construction activity related sources of pollution, and (ii) set forth procedures and methods (including land use requirements) to control to the extent feasible such sources;

(I) a process to (i) identify, if appropriate, salt water intrusion into rivers, lakes, and estuaries resulting from reduction of fresh water flow from any cause, including irrigation, obstruction, ground water extraction, and diversion, and (ii) set forth procedures and methods to control such intrusion to the extent feasible where such procedures and methods are otherwise a part of the waste treatment management plan;

(J) a process to control the disposition of all residual waste generated in such area which could affect water quality; and (K) a process to control the disposal of pollutants on land or in subsurface excavations within such area to protect ground and surface water quality.

(3) Areawide waste treatment management plans shall be certified annually by the Governor or his designee (or Governors or their designees, where more than one State is involved) as being consistent with applicable basin plans and such areawide waste treatment management plans shall be submitted to the Administrator for his approval.

(4) (4) Whenever the Governor of any State determines (and notifies the Administrator) that consistency with a statewide regulatory program under section 303 so requires, the requirements of clauses (F) through (K) of paragraph (2) of this subsection shall be developed and submitted by the Governor [to the Administrator for application to all regions within such State] to the Administrator for approval for application to a class or category of activity throughout such State.

para

(B) Any program submitted under subparagraph (A) of this graph which, in whole or in part, is to control the discharge or other placement of dredged or fill material into the navigable waters shall include the following:

(i) A consultation process which includes the State agency with primary jurisdiction over fish and wildlife resources.

(ii) A process to identify and manage the discharge or other placement of dredged or fill material which adversely affects navigable waters, which shall complement and be coordinated with a State program under section 404 conducted pursuant to this Act.

(iii) A process to assure that any activity conducted pursuant to a best management practice will comply with the guidelines established under section 404(b)(1), and sections 307 and 403 of this

Act.

(iv) A process to assure that any activity conducted pursuant to a best management practice can be terminated or modified for cause including, but not limited to, the following:

(I) violation of any condition of the best management practice;

(II) change in any activity that requires either a temporary or permanent reduction or elimination of the discharge pursuant to the best management practice.

(v) A process to assure continued coordination with Federal and Federal-State water-related planning and reviewing processes, including the National Wetlands Inventory.

(C) If the Governor of a State obtains approval from the Administrator of a statewide regulatory program which meets the requirements of subparagraph (B) of this paragraph and if such State is administering a permit program under section 404 of this Act, no person shall be required to obtain an individual permit pursuant to such section, or to comply with a general permit issued pursuant to such section, with respect to any appropriate activity within such State for which a best management practice has been approved by the Administrator under

« ÀÌÀü°è¼Ó »