...following: (1) The contractor shall promptly, and before such conditions are disturbed, notify the claimant in writing of: (1) Subsurface or latent physical conditions at the site differing materially from those listed in this contract, or (ii) Unknown physical conditions at the site, of an unusual nature, differing... | |
| 1973 - 740 페이지
...shall be allowed if asserted after final payment under this contract. 4. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writine? of: (1) Subsurface or latent physical conditions at the site differing materially from those... | |
| 1971 - 664 페이지
...shall be allowed if asserted after final payment under this contract. 4. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing1 of: (1) Subsurface or latent physical conditions at the site differing materially from those... | |
| 1968 - 1348 페이지
...such conditions are dlslurlted. notify the Contracting Officer in writing of: (a) subsurface or Intent physical conditions at the site differing materially from those indicated In this contract, or (b) unknown physical conditions at the site, of nn unusual nature, din. -nut: materially from those... | |
| United States. Congress. House. Appropriations - 1961 - 336 페이지
...herein provided, no charge for any extra work or material will be allowed. > 4. CHANGED CONDITIONS The Contractor shall promptly, and before such conditions...physical conditions at the site, of an unusual nature, ditfering materially from those ordinarily encountered and generally recognized us inhering in work... | |
| United States. Bureau of Public Roads - 1969 - 472 페이지
...shall be allowed if asserted after final payment under this contract. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions...physical conditions at the site differing materially from these indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature,... | |
| United States. Department of the Interior - 1957 - 624 페이지
...requirements. Clause 4 stated that, should conditions of the type described in that clause be encountered, "the Contractor shall promptly, and before such conditions...disturbed, notify the Contracting Officer in writing" of the conditions encountered, and that any claim of the Contractor for an equitable adjustment on account... | |
| United States. Department of the Interior - 1971 - 376 페이지
...original estimate for bid purposes of 815,000 tons of borrow material. The ad«"4. CHANGED CONDITIONS "The Contractor shall promptly, and before such conditions...disturbed, notify the Contracting Officer In writing of : (a) subsurface or latent physical conditions at the site differing materially from those Indicated... | |
| United States. Department of the Interior - 1972 - 536 페이지
...physical conditions at the site differing materially from those Indicated in this contract, or (b) unknown physical conditions at the site, of an unusual...nature, differing materially from those ordinarily The Government defends along several lines : One, the claim is defeated by lack of notice under the... | |
| United States. Department of the Interior - 1975 - 1126 페이지
...written notice as therein required * * • ***** 4. DIFFERING SITE CONDITIONS (a) The Contractor shull promptly, and before such conditions are disturbed,...notify the Contracting Officer in writing of: (1) Sul»surface or latent physical conditions at the site differing materially from those indicated in... | |
| |