" Officer grants a further period of time before the date of final payment under the contract), notifies the ContractIng Officer In writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend... "
Cases Decided in the Court of Claims of the United States - 346 페이지
저자: United States. Court of Claims - 1948
전체보기 - 도서 정보

Code of Federal Regulations: Containing a Codification of Documents of ...

1977
...facts and the extent of the delay and extend the time for completing the work when, in his judgement, the findings of fact justify such an extension, and his findings of fact shall be final and conclusive on the parties, subject only to appeal as provided in the Remedies clause...
전체보기 - 도서 정보

Code of Federal Regulations: Containing a Codification of Documents of ...

1978 - 1170 페이지
...delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the tune for completing the work when, in his judgment, the...justify such an extension, and his findings of fact shall be final and conclusive on the parties subject only to appeal as provided in the clause of this...
전체보기 - 도서 정보

Code of Federal Regulations: Containing a Codification of Documents of ...

1978 - 740 페이지
...Owner in writing of the causes of delay. The Owner shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgement, the findings of fact justify such an extension, and his findings of fact shall be final...
전체보기 - 도서 정보

Military construction appropriations for 1982: hearings before a ..., 파트 5

United States. Congress. House. Committee on Appropriations. Subcommittee on Military Construction Appropriations - 1981 - 608 페이지
...writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work...justify such an extension, and his findings of fact shall be final and conclusive on tne parties, subject only to appeal as provided in the "Disputes"...
전체보기 - 도서 정보

Code of Federal Regulations: Containing a Codification of Documents of ...

1982 - 550 페이지
...Officer shall ascertain the facts and the extent of the delay and extend the time for completing the woik when, in his judgment, the findings of fact justify such an extension, and his findings of fact shall be final and conclusive on the parties, subiect only to appeal as provided in Clause G of these...
전체보기 - 도서 정보

Code of Federal Regulations: Containing a Codification of Documents of ...

1983 - 806 페이지
...Officer of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work...judgment, the findings of fact justify such an extension. Where the Contractor's right to proceed with all or part of the work is terminated within less than...
전체보기 - 도서 정보

The Code of Federal Regulations of the United States of America

1984 - 992 페이지
...delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the lime for completing the work when, in his judgment, the...conclusive on the parties hereto, subject only to appeal by the architectengineer to the head of the agency or his designee in accordance with Article hereof...
전체보기 - 도서 정보

Code of Federal Regulations: Containing a Codification of Documents of ...

1988 - 872 페이지
...owner in writing of the causes of delay. The owner shall ascertain the facts and the extent of the delay and extend the time for completing the work...judgment, the findings of fact justify such an extension. His findings of fact shall be final and conclusive on the parties, subject only to appeal as the remedies...
전체보기 - 도서 정보

The Code of Federal Regulations of the United States of America

1999 - 724 페이지
...writing of the causes of delay. The contracting officer shall ascertain the facts and the extent of the delay and extend the time for completing the work...findings of fact thereon shall be final and conclusive on (.he parties hereto, subject only to appeal by the architect-engineer to the head of the agency or...
전체보기 - 도서 정보

The Code of Federal Regulations of the United States of America

1967 - 694 페이지
...Contracting Officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay and extend the time for completing the work...conclusive on the parties hereto, subject only to appeal by the Contractor to the Commission in accordance with the article entitled "Disputes." (c) Liability...